Lessons Learned

Capture, govern, and apply lessons across the data center development program.

Lessons Captured

64

Implemented

41

+7 this quarter

Open Recommendations

12

Under review

Recurring Themes

5

Tracked

Order long-lead transformers at 30% design

High
Procurement

Late transformer orders drove a 21-day energization slip. Commit major electrical long-lead items at 30% design maturity with a lead-time buffer.

Stage commissioning QA before turnover

High
Quality

Incomplete documentation at turnover created NCR aging. Run targeted QA walkdowns and enforce package acceptance criteria before system turnover.

Plan third-party commissioning capacity early

Medium
People

Electrical commissioning workload peaked 22% above internal staffing. Pre-arrange third-party support contracts for predictable peak windows.

Escalate utility agreements at portfolio gate

High
Strategy

Utility interconnection became the dominant portfolio risk. Treat service agreements as executive gate items rather than project-level tasks.

Resequence electrical rooms to absorb slips

Medium
Delivery

Resequencing electrical room work allowed construction to continue despite procurement delays without impacting the critical path.