Mission Performance Dashboard

Business value, capacity delivery, energy performance, and revenue readiness

AI Insight

DCDM Intelligence

Campus Alpha is tracking 6 weeks ahead on revenue readiness due to early utility energization and improved commissioning package closure. However, energy cost per MW is trending 4.8% above target. Recommend reviewing cooling optimization before tenant turnover.

Planned Capacity

96 MW

Capacity Ready

42 MW

+8 MW QoQ

Revenue Readiness

74%

+6% vs plan

Cost per MW

$9.8M

+4.8% over target

PUE Forecast

1.27

-0.02 improving

WUE Forecast

0.42 L/kWh

On target

Tenant Commitment

68%

+5% QoQ

ESG Readiness

82%

+3% QoQ

Capacity Delivered vs Planned

Cumulative MW across portfolio

Revenue Readiness

Portfolio gauge

74%ready for revenue

Cost per MW Trend

$ millions, trailing 6 months

Energy Performance

Forecast vs target

ESG Scorecard

Readiness by pillar

Environmental84%
Social79%
Governance83%

Campus Performance

Capacity, energy, and revenue readiness by campus

CampusPlanned MWReady MWRevenue DatePUEStatus
Campus Alpha48 MW24 MWQ3 20261.25On Track
Campus Beta32 MW12 MWQ4 20261.31Watch
Campus Gamma16 MW6 MWQ1 20271.28At Risk