Systems Tested
43%
+5% MoM
IST Readiness
38%
Behind plan
Punch Items Open
214
-26 closed
Turnover Complete
31%
+3% MoM
System Readiness
Commissioning progress and open punch items by system
| System | Progress | Punch Items | Status |
|---|---|---|---|
| Medium Voltage | 58% | 28 | Watch |
| Low Voltage | 64% | 22 | On Track |
| UPS | 41% | 31 | At Risk |
| Generators | 36% | 24 | At Risk |
| Chilled Water | 52% | 19 | Watch |
| CRAH Units | 60% | 16 | On Track |
| Fire Alarm | 72% | 9 | On Track |
| BMS | 33% | 27 | At Risk |
| Security | 47% | 14 | Watch |
| Network | 55% | 18 | Watch |