EPC Delivery Intelligence Dashboard

Design, procurement, construction, commissioning, and turnover execution

AI Insight

DCDM Intelligence

Procurement is now the main constraint to construction progress. Transformer delivery is forecasted 21 days late, which may impact energization and integrated systems testing. Recommend mitigation through resequencing electrical rooms and early FAT documentation review.

Design Completion

87%

+4% MoM

IFC Package Readiness

76%

+6% MoM

Procurement Health

69%

-3% MoM

Construction Progress

58%

+5% MoM

Commissioning Readiness

44%

Behind plan

Open RFIs

126

+18 this month

Long Lead At Risk

7

+2 items

Turnover Complete

31%

+3% MoM

Construction S-Curve

Planned vs actual % complete

Commissioning Readiness

Systems ready for IST

44%commissioning ready

EPC Phase Progress

Completion across delivery phases

Design87%
Procurement69%
Construction58%
Commissioning44%
Turnover31%

RFI Aging

Open RFIs by age bucket

Workstream Progress

Planned vs actual by discipline

WorkstreamPlanned %Actual %VarianceStatus
Civil/Site82%79%-3Watch
Structural76%78%+2On Track
Electrical61%52%-9At Risk
Mechanical58%55%-3Watch
Controls/BMS38%29%-9At Risk
Commissioning42%31%-11At Risk

Long Lead Items

Critical procurement tracking

ItemVendorNeed DateForecast DateRisk
230kV TransformerHitachiAug 12Sep 3High
Switchgear LineupSiemensJul 18Jul 25Medium
CRAH UnitsVertivSep 1Aug 28Low
GeneratorsCaterpillarOct 4Oct 20High
UPS ModulesSchneiderAug 30Sep 7Medium